Elevator - Proposals, 1895

 File — Box: 1, Folder: 1
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1895

Heating & Ventilating Systems - 1895-1897 - Correspondence

 File — Box: 1, Folder: 2
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Heating & Ventilating Systems - 1895-1897 - Contract

 File — Box: 1, Folder: 3
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Heating & Ventilating Systems - 1895-1897 - Notes

 File — Box: 1, Folder: 4
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Heating & Ventilating Systems - 1895-1897 - Specifications

 File — Box: 1, Folder: 5
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Exterior Brick Wall & Landscaping - Correspondence, 1899

 File — Box: 1, Folder: 6
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1899

Trustees Room Remodelling - Specifications, 1899

 File — Box: 1, Folder: 7
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1899

Friday Club Room Renovation - Correspondence and Proposals, 1902

 File — Box: 1, Folder: 8
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1902

Reinforcement of Library Floors - Correspondence and Proposal, 1904-1912

 File — Box: 1, Folder: 9
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1904-1912

Boiler Plant - Correspondence and Specifications, 1905-1906

 File — Box: 1, Folder: 10
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1905-1906

Second Floor East Room Remodelling - Correspondence, 1923

 File — Box: 1, Folder: 11
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1923

Exhibit Room Furnishings - Notes, 1924

 File — Box: 1, Folder: 12
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1924

Ayer Vault Construction - Contracts, 1925-1926

 File — Box: 1, Folder: 13
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1925-1926

Ayer Vault Construction - Correspondence and Notes, 1925-1926

 File — Box: 1, Folder: 14
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1925-1926

Account of Repairs and Report, 1939-1943

 File — Box: 1, Folder: 15
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1939-1943

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Contract

 File — Box: 1, Folder: 16
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Correspondence

 File — Box: 1, Folder: 17
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Guarantees

 File — Box: 1, Folder: 18
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Notes

 File — Box: 1, Folder: 19
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Progress Reports, 1944

 File — Box: 1, Folder: 20
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...
Dates: 1944

Roofing, Heating, Fifth Floor Completion and Repairs - 1944-1946 - Progress Reports, 1945

 File — Box: 1, Folder: 21
Identifier: NL Archives 13/00/03
Scope and Contents From the Series: Although the Newberry Library was officially opened in November of 1893, portions of the interior structure were not finished until the 1940's when further space was required. In addition, as needs and technology changed, renovations of existing rooms and systems took place. Major projects have included the 1895-1897 renovation of the heating and ventilating systems, the 1899 and 1923 Trustee Room remodellings, the 1925-1926 Ayer Vault construction, the 1944-1946 fifth floor completion and...